WGI Icon_Green (1)
WGI Projects
Project Experience

Learn more about successful projects from some of our clients.

Plan Your Next Project!

Kick-start your next project with this quick step-by-step intake form.
About
WGI

WGI is a national design firm creatively transforming infrastructure and real estate through tech-driven services.

Our
Locations

You’ve seen our award-winning team, proven expertise, and industry authority. Now let’s make your next project a success.

Meet Our
Leadership Team

Our Executive Leadership Team and Practice Area Leaders bring decades of experience and client successes to your next project.

Our Practice Area Leadership

Our nationwide team of engineers, surveyors, planners, and architects offers
market-leading experience.

Firm Registrations

WGI holds nationwide registrations to perform engineering, surveying, architecture, and environmental science services.
WGI
Insights Blog

Our blog covers client interests like infrastructure, real estate, regulations, and smart, connected communities.

Whitepapers & Publications

Our whitepapers highlight our design experts' innovative insights and best practices for the AEC industry.

News &
Press Releases

Dedicated to your success, we invite you to subscribe to our newsletter for the latest news, case studies, and insights.

WGI
Media Room

Our passionate design professionals frequently share their expertise at webinars and virtual events.

Post Tags

Here's How NOAA Atlas 14 Detention Rates Impact Projects in the City of Houston

On July 1, 2020, the City of Houston published a new Infrastructure Design Manual (IDM) acknowledging that Harris County and Harris County Flood Control adopted the new Atlas 14 data on June 4, 2019. The City stated that they would consider and edit the new Atlas 14 information for a future release date. Fast forward to January 4, 2021, and the City of Houston has prepared and signed a supplement to chapter 9 of the IDM, bringing its detention requirements more in line with what both Harris County and Harris County Flood Control adopted in 2019.

What is detention, and how do the changes affect my project?

Detention is storing a calculated volume of rainwater and releasing it at a controlled rate so as to not overwhelm the existing stormwater infrastructure. Detention ponds and other stormwater infrastructure play a major role in the way a site is designed, and the upcoming changes will result in detention pond designs becoming much larger in size. This will likely add to project costs and occupy additional valuable acreage that could otherwise be utilized for a larger development area.

When do the changes take effect?

These changes are scheduled to go into effect on March 31, 2021, and will greatly impact detention rates for sites of all sizes. Current projects will be grandfathered from the new requirements as long as plans are submitted to the City for review prior to the effective date. Changes to section 9.2.01.H. of the IDM are summarized below: Detention Waivers:
  • A timing analysis can no longer be performed to avoid detention requirements.
Calculation of Detention Volume:
  • Single Family lots less than 7,500 sq. ft are not required to provide detention if the impervious area is less than or equal to 65%. If the impervious area is greater than 65% of the lot area, a detention rate of 0.75 ac-ft/ac is required.
  • Tract sizes less than one acre that does not fall into the single-family lot category will be required to detain at a rate of 0.75 ac-ft/ac.
  • Tract sizes between 1 and 20 acres will be required to detain at a rate determined from the following chart: drainage chart
  • Tract sizes greater than 20 acres: Detention calculation will be per the most current version of the HCFCD PCPM.

Do you still have questions?